ANF LINGEN

1979 nahm Exxon Nuclear in Lingen eine Fabrik für Kernkraftwerksbrennelemente in Betrieb. Seit 1987 heißt das Unternehmen Advanced Nuclear Fuels (ANF); über Siemens kam es 2001 zu Framatome. Am Seitenkanal werden weiterhin Brennelemente aus angereichertem Uran hergestellt, seit April 2023 ausschließlich für ausländische Kernkraftwerke. Im Juli 2026 wurde eine umstrittene Erweiterung für Reaktoren russischer Bauart genehmigt.

In 1979, Exxon Nuclear began operating a nuclear fuel assembly plant in Lingen. The company has been known as Advanced Nuclear Fuels (ANF) since 1987; it passed through Siemens to Framatome in 2001. The plant on the Ems side canal continues to manufacture fuel assemblies from enriched uranium, exclusively for nuclear power stations outside Germany since April 2023. In July 2026, a controversial expansion to supply Russian-designed reactors was authorised.

Von Exxon zu ANF

Am Seitenkanal in Lingen errichtete der amerikanische Mineralölkonzern Exxon eine Brennelementfabrik. Seine 1975 gegründete deutsche Tochter Exxon Nuclear GmbH erhielt am 18. Januar 1979 die erste Teilbetriebsgenehmigung. Anfangs wurden angelieferte Urandioxidtabletten in Brennstäbe gefüllt und zu Brennelementen für Druck- und Siedewasserreaktoren zusammengesetzt. Mit dem Nukleargeschäft von Exxon übernahm Siemens auch das amerikanische Brennelementwerk in Richland (Washington). 1987 erhielt die deutsche Gesellschaft den Namen Advanced Nuclear Fuels GmbH (ANF). Ein Jahr später begann in Lingen auch die Fertigung eigener Brennstofftabletten aus angeliefertem Urandioxidpulver. 1994 ging die Trockenkonversion in Betrieb: Seitdem kann das Werk das aus der Urananreicherung kommende Uranhexafluorid selbst in Urandioxidpulver umwandeln. Der Fertigungsweg vom angereicherten Ausgangsmaterial bis zum fertigen Brennelement lag nun an einem Standort.

Zwei Behälter, die nicht leer waren

Im Mai 1990 wurden in Lingen zwei Behälter mit insgesamt rund 147 Kilogramm angereichertem Urandioxid versehentlich als Leergut gekennzeichnet. Sie gelangten über Luxemburg per Frachtflugzeug zur amerikanischen ANF in Richland, der damaligen Muttergesellschaft des Lingener Unternehmens. Dort wurde der Inhalt entdeckt. Die Europäische Kommission stellte erhebliche Mängel bei der Kernmaterialüberwachung fest und unterstellte die entsprechenden Kontrollverfahren des Lingener Betriebs für vier Monate einer externen Verwaltung. ANF klagte dagegen; der Europäische Gerichtshof wies die Klage am 21. Januar 1993 ab.

Ein Werk für den internationalen Markt

1995 führte Siemens die Lingener Brennelementfertigung, die mechanische Komponentenfertigung in Karlstein und die Hüllrohrfertigung in Duisburg organisatorisch bei ANF zusammen. 2001 wechselte das Unternehmen mit dem Siemens-Brennelementgeschäft zu Framatome ANP, später Areva NP; seit 2018 firmiert der französisch geführte Konzern wieder als Framatome.

Die Fertigung am Seitenkanal umfasst heute die Umwandlung von Uranhexafluorid zu Uranoxidpulver, das Pressen und Sintern keramischer Brennstofftabletten, die Herstellung der Brennstäbe und ihren Zusammenbau zu Brennelementen. Verarbeitet wird Uran mit höchstens fünf Prozent Uran-235. Genehmigt sind bis zu 800 Tonnen Uran jährlich für die Konversion und 650 Tonnen für die übrigen Fertigungsstufen; diese Zahlen bezeichnen Kapazitätsgrenzen, keine tatsächliche Jahresproduktion.

Seit 1995 ist Lingen die einzige deutsche Fabrik für Uranbrennelemente. Schon vor dem deutschen Atomausstieg belieferte sie zahlreiche Kraftwerke im Ausland. 2014 gingen nach Angaben der Bundesregierung 774 Brennelemente aus Lingen an Kunden, darunter Kraftwerke in Frankreich und Finnland. Seit der Abschaltung der letzten deutschen Kernkraftwerke am 15. April 2023 produziert das Werk ausschließlich für ausländische Kernkraftwerke. Die Brennelementfertigung in Lingen und die Urananreicherung in Gronau sind vom gesetzlichen Atomausstieg nicht erfasst; beide besitzen unbefristete Genehmigungen. Atomkraftgegner fordern deshalb auch ihre Stilllegung.

Neue Brennelemente für osteuropäische Reaktoren

Stand der Genehmigungs- und Rechtslage: 28. Oktober 2026.

Am 22. Juli 2026 genehmigte Niedersachsen ANF, zusätzlich sechseckige Brennelemente für Druckwasserreaktoren sowjetischer beziehungsweise russischer Bauart (WWER/VVER) herzustellen. Geplant ist die Lizenzfertigung mit Technik des russischen Staatskonzerns Rosatom beziehungsweise seiner Brennstofftochter TVEL für Kernkraftwerke in Mittel- und Osteuropa. Die Genehmigung enthält besondere Auflagen: Angehörige der russischen Unternehmen dürfen das Werksgelände grundsätzlich nicht betreten; Lizenzmaschinen müssen sicherheitstechnisch geprüft und von der übrigen Werks-IT getrennt werden.

Gegen die Erweiterung waren bei der öffentlichen Auslegung 2024 rund 11.000 Einwendungen eingegangen. Niedersachsens Umweltminister Christian Meyer kritisierte die Zusammenarbeit wegen der Sicherheitsrisiken und des russischen Angriffskriegs gegen die Ukraine. Die Bundesatomaufsicht hielt eine Versagung der Genehmigung nach geltendem Atomrecht jedoch für nicht möglich, sofern die Anforderungen durch Auflagen erfüllt würden. Am 10. September 2026 erhob der BUND Klage. Am 5. Oktober ordnete Niedersachsen die sofortige Vollziehung an; ANF begann daraufhin mit Vorbereitungen für die neue Fertigung.

From Exxon to ANF

The American oil company Exxon built a fuel assembly plant beside the Ems side canal in Lingen. Its German subsidiary, Exxon Nuclear GmbH, established in 1975, received its first partial operating licence on 18 January 1979. Initially, uranium dioxide pellets delivered to the plant were loaded into fuel rods, which were then assembled into fuel assemblies for pressurised and boiling water reactors. When Siemens acquired Exxon's nuclear business, it also took over the American fuel fabrication plant in Richland, Washington. In 1987, the German company was renamed Advanced Nuclear Fuels GmbH (ANF). A year later, Lingen also began making its own fuel pellets from supplied uranium dioxide powder. Dry conversion started in 1994: since then, the plant has been able to convert uranium hexafluoride arriving from enrichment facilities into uranium dioxide powder itself. All stages, from the enriched starting material to the finished fuel assembly, were now located at a single site.

Two containers that were not empty

In May 1990, two containers holding a total of approximately 147 kilograms of enriched uranium dioxide were mistakenly labelled as empty. They travelled via Luxembourg on a cargo aircraft to the American ANF facility in Richland, then the parent company of the Lingen operation. Their contents were discovered there. The European Commission identified serious shortcomings in nuclear material safeguards and placed the relevant control procedures at the Lingen plant under external administration for four months. ANF challenged the decision; the European Court of Justice dismissed its action on 21 January 1993.

A plant serving the international market

In 1995, Siemens brought together fuel assembly production in Lingen, mechanical component manufacture in Karlstein and fuel cladding tube manufacture in Duisburg under ANF. In 2001, the company moved with Siemens' fuel business to Framatome ANP, later Areva NP; the French-led group has once again operated under the name Framatome since 2018.

Production at the canal-side plant now covers conversion of uranium hexafluoride into uranium oxide powder, pressing and sintering ceramic fuel pellets, manufacturing fuel rods and assembling them into fuel assemblies. The plant processes uranium enriched to no more than five per cent uranium-235. Authorised capacities are up to 800 tonnes of uranium per year for conversion and 650 tonnes for the other fabrication stages; these figures are capacity limits, not actual annual output.

Since 1995, Lingen has been Germany's only uranium fuel assembly plant. Even before Germany's nuclear phase-out, it supplied numerous power stations abroad. According to the German government, 774 fuel assemblies were shipped from Lingen to customers in 2014, including nuclear power stations in France and Finland. Since Germany's last nuclear power stations shut down on 15 April 2023, the plant has produced exclusively for foreign nuclear power stations. Fuel fabrication at Lingen and uranium enrichment at Gronau are not covered by the statutory nuclear phase-out; both hold licences without a fixed expiry date. Anti-nuclear campaigners therefore also demand their closure.

New fuel assemblies for Eastern European reactors

Regulatory and legal position as at 28 October 2026.

On 22 July 2026, Lower Saxony authorised ANF to manufacture hexagonal fuel assemblies for Soviet- or Russian-designed pressurised water reactors (WWER/VVER). The plan is for licensed manufacture using technology from the Russian state nuclear corporation Rosatom, or its fuel subsidiary TVEL, for nuclear power stations in Central and Eastern Europe. The authorisation imposes special conditions: staff of the Russian companies are generally barred from entering the plant; machinery supplied under licence must undergo security assessments and be kept separate from the rest of the plant's IT systems.

During the public consultation in 2024, around 11,000 objections to the expansion were submitted. Lower Saxony's environment minister Christian Meyer criticised the cooperation on grounds of security risks and Russia's war of aggression against Ukraine. The federal nuclear regulator, however, considered that under the applicable nuclear law the licence could not be refused if the requirements could be met through conditions. On 10 September 2026, BUND brought a legal challenge. On 5 October, Lower Saxony ordered immediate enforceability of the licence, after which ANF began preparations for the new production line.

Technische EckdatenKey facts
Verfahren
Fertigung von Uranbrennelementen (Trockenkonversion seit 1994)
Betreiberin
Advanced Nuclear Fuels GmbH (ANF)
Eigner
Framatome
Erste Teilbetriebsgenehmigung
18.1.1979nicht gleich Produktionsbeginn
Genehmigte Kapazität Konversion
bis zu 800 t Uran/JahrStand 28.10.2026
Genehmigte Kapazität übrige Fertigung
bis zu 650 t Uran/JahrStand 28.10.2026
Status
in Betrieb
Technische EckdatenKey facts
Process
Uranium fuel assembly fabrication (dry conversion since 1994)
Operator
Advanced Nuclear Fuels GmbH (ANF)
Owner
Framatome
First partial operating licence
18 January 1979not necessarily the start of production
Authorised conversion capacity
up to 800 tonnes of uranium/yearas at 28 October 2026
Authorised capacity for other fabrication stages
up to 650 tonnes of uranium/yearas at 28 October 2026
Status
operating