ATUCHA II
Atucha II ist ein von Siemens/Kraftwerk Union entwickelter Schwerwasser-Druckwasserreaktor mit 745 Megawatt elektrischer Bruttoleistung. Sein Bau begann 1981, wurde 1994 eingestellt und ab 2006 unter argentinischer Verantwortung vollendet. 2014 lieferte der Block erstmals Strom; die Genehmigung für den kommerziellen Betrieb folgte 2016. Er erhielt 2026 eine neue Betriebsgenehmigung bis 2036.
Atucha II is a heavy-water pressurised reactor developed by Siemens/Kraftwerk Union, with a gross electrical output of 745 megawatts. Construction began in 1981, was halted in 1994 and was completed under Argentine leadership from 2006. The unit supplied electricity for the first time in 2014; authorisation for commercial operation followed in 2016. In 2026, it received a new operating licence valid until 2036.
Atucha II wurde als deutlich größere Fortentwicklung des ersten Blocks entworfen. Sein Reaktordruckbehälter ist rund 14 Meter hoch und gut sieben Meter breit; er enthält 451 senkrechte Brennstoffkanäle. Die Brennelemente waren ursprünglich für Natururan ausgelegt. Schweres Wasser führt die Spaltungswärme durch zwei Primärkreisläufe mit je einem Dampferzeuger ab. Vier weitere Kreisläufe führen Wärme aus dem Moderatorsystem ab. Die Konstruktion verband das besondere Schwerwasserkonzept von Atucha I mit sicherheitstechnischen Entwicklungen aus den späteren KWU-Druckwasserreaktoren. Auch hier können Brennelemente während des Betriebs gewechselt werden.
Argentinien vergab den Auftrag für den zweiten Block 1980 an Siemens/KWU. Die Bauarbeiten begannen nach der internationalen Kraftwerksstatistik im Juli 1981; die argentinische Atomaufsicht nennt 1982 als Beginn der eigentlichen Errichtung. Finanzierungsprobleme und politische Umbrüche verzögerten das Projekt. 1994 wurden die Arbeiten bei einem Fertigstellungsgrad von rund 80 Prozent weitgehend eingestellt. Erst mit dem argentinischen Atomprogramm von 2006 wurde der Bau wieder aufgenommen. Da Siemens das Geschäft mit Kernreaktoren inzwischen aufgegeben hatte, übernahm Nucleoeléctrica Argentina die Verantwortung für Auslegung und Fertigstellung. Mit einer Vereinbarung von 2006 übertrug Siemens die Konstruktionsrechte, Berechnungswerkzeuge und technischen Unterlagen und unterstützte weiterhin den konventionellen Anlagenteil. Areva NP, in der Teile des früheren KWU-Reaktorgeschäfts aufgegangen waren, entsandte Fachleute für Konstruktion, Genehmigung, Montage und Inbetriebsetzung. Auch die kanadische AECL und weitere internationale Einrichtungen leisteten technische Unterstützung. Die praktische Projektführung blieb argentinisch.
Am 3. Juni 2014 wurde Atucha II erstmals kritisch, am 27. Juni mit dem Netz synchronisiert. Im Februar 2015 erreichte die Anlage die volle Leistung. Die argentinische Atomaufsicht erteilte am 26. Mai 2016 die Genehmigung für den kommerziellen Betrieb.
Bei einer Inspektion im Herbst 2022 wurde festgestellt, dass sich einer von vier inneren Abstandhaltern im Reaktordruckbehälter gelöst hatte. Statt den Reaktor weitgehend zu zerlegen, entwickelte der Betreiber ein Verfahren, das Bauteil unter Wasser zu zerschneiden und in Teilen zu bergen. Anschließend wurden die drei verbliebenen Elemente gesichert. Nach rund zehn Monaten Stillstand genehmigte die Atomaufsicht im August 2023 den Wiederanlauf. Im Mai 2026 verlängerte sie die Betriebsgenehmigung bis zum 26. Mai 2036. Für abgebrannte Brennelemente entsteht am Standort zudem ein neues Trockenlager (Stand Oktober 2026).
Atucha II was designed as a much larger development of the first unit. Its reactor pressure vessel is about 14 metres high and more than seven metres wide, containing 451 vertical fuel channels. The fuel assemblies were originally designed for natural uranium. Heavy water carries away the heat from fission through two primary coolant loops, each with its own steam generator. Four further circuits remove heat from the moderator system. The design combined Atucha I's distinctive heavy-water concept with safety developments from KWU's later pressurised water reactors. Fuel assemblies can also be replaced while the reactor is operating.
Argentina awarded the contract for the second unit to Siemens/KWU in 1980. According to international power-station statistics, construction began in July 1981; Argentina's nuclear regulator gives 1982 as the start of construction proper. Financing difficulties and political upheaval delayed the project. In 1994, work largely ceased when the plant was about 80 per cent complete. Construction resumed only with Argentina's nuclear programme of 2006. By then Siemens had withdrawn from the nuclear reactor business, so Nucleoeléctrica Argentina assumed responsibility for engineering and completion. Under a 2006 agreement, Siemens transferred the design rights, calculation tools and technical documentation and continued to support the conventional part of the plant. Areva NP, which had taken over parts of KWU's former reactor business, sent specialists to assist with design, licensing, assembly and commissioning. Canada's AECL and other international organisations also provided technical support. Practical project management remained in Argentine hands.
Atucha II first achieved criticality on 3 June 2014 and was synchronised with the grid on 27 June. In February 2015, the plant reached full power. Argentina's nuclear regulator granted authorisation for commercial operation on 26 May 2016.
During an inspection in autumn 2022, it was discovered that one of four internal spacers inside the reactor pressure vessel had become detached. Rather than largely dismantle the reactor, the operator developed a method of cutting the component underwater and retrieving it in sections. The three remaining components were then secured. After about ten months offline, the regulator authorised restart in August 2023. In May 2026, it extended the operating licence to 26 May 2036. A new dry-storage facility for spent fuel is also being built at the site (as at October 2026).
- Reaktortyp
- Schwerwasser-Druckwasserreaktor
- Hersteller
- Kraftwerk Union (KWU)
- Betreiber
- Nucleoeléctrica Argentina S.A.
- Leistung thermisch
- 2.175 MW nach Betreiberangabe
- Leistung elektrisch
- 745 MW brutto, rund 690 MW netto
- Primärkreisläufe
- 2
- Brennelemente
- 451
- Brennstoffkanäle
- 451
- Erstkritikalität
- 3.6.2014
- Netzanschluss
- 27.6.2014
- Kommerzieller Betrieb
- ab 26.5.2016
- Status
- in Betrieb
- Siemens/KWU-Entwurf, Fertigstellung unter argentinischer Projektleitung mit internationaler Fachunterstützung
- vier Moderatorkreisläufe
- ursprünglich für Natururan ausgelegt
- in Betrieb, Lizenz bis 26.5.2036 (Stand Oktober 2026)
- Druckbehälterbauart mit senkrechten Brennstoffkanälen
Betreiber
Atucha II wird von Nucleoeléctrica Argentina betrieben. Die Gesellschaft ist staatlich kontrolliert und betreibt auch Atucha I und Embalse.
- Reactor type
- Heavy-water pressurised reactor
- Manufacturer
- Kraftwerk Union (KWU)
- Operator
- Nucleoeléctrica Argentina S.A.
- Thermal output
- 2,175 MW according to the operator
- Electrical output
- 745 MW gross, approximately 690 MW net
- Primary coolant loops
- 2
- Fuel assemblies
- 451
- Fuel channels
- 451
- First criticality
- 3 June 2014
- Grid connection
- 27 June 2014
- Commercial operation
- from 26 May 2016
- Status
- Operational
- Siemens/KWU design, completed under Argentine project management with international specialist support
- Four moderator circuits
- Originally designed for natural uranium
- Operational, licensed until 26 May 2036 (as at October 2026)
- Pressure-vessel design with vertical fuel channels
Operator
Atucha II is operated by Nucleoeléctrica Argentina. The company is state-controlled and also operates Atucha I and Embalse.
Glossar:Glossary:
Schwerwasserreaktor
Kernreaktor, der schweres Wasser (D₂O) als Moderator zur Abbremsung der Neutronen verwendet. Das Kühlmittel muss dagegen nicht aus schwerem Wasser bestehen. Beim MZFR in Karlsruhe und den Atucha-Reaktoren in Argentinien diente schweres Wasser sowohl zur Moderation als auch zur Kühlung; beide sind Druckwasserreaktoren mit Reaktordruckbehälter. Niederaichbach und Lucens waren hingegen schwerwassermoderierte, mit Kohlendioxid gekühlte Druckröhrenreaktoren. Auch die kanadischen CANDU-Reaktoren besitzen Druckröhren; bei ihnen wird schweres Wasser sowohl als Moderator als auch als Kühlmittel verwendet, in getrennten Kreisläufen.
Glossar:Glossary:
Heavy-Water Reactor
A nuclear reactor that uses heavy water (D₂O) as a moderator to slow neutrons. The coolant does not, however, have to be heavy water. At the MZFR in Karlsruhe and the Atucha reactors in Argentina, heavy water served both as moderator and coolant; both are pressurised water reactors with reactor pressure vessels. Niederaichbach and Lucens, by contrast, were heavy-water-moderated, carbon-dioxide-cooled pressure-tube reactors. Canadian CANDU reactors also have pressure tubes; they use heavy water as both moderator and coolant, in separate circuits.