EUROCHEMIC

In Dessel entstand zwischen 1960 und 1966 eine von 13 europäischen Staaten getragene Wiederaufarbeitungsanlage. Eurochemic sollte Kernbrennstoff aufarbeiten und den Partnerländern eigenes technisches Wissen vermitteln. Der Betrieb endete bereits 1974. Danach wurden die hochradioaktiven Abfälle verglast und die Anlage jahrzehntelang rückgebaut. Auf dem Gelände arbeitet heute der belgische Abfallbehandlungsbetrieb Belgoprocess.

Between 1960 and 1966, a reprocessing plant backed by 13 European countries was built at Dessel. Eurochemic was intended to reprocess nuclear fuel and enable participating countries to acquire their own technical expertise. Operations ceased as early as 1974. The high-level waste was subsequently vitrified and the plant dismantled over several decades. Today, the Belgian waste treatment company Belgoprocess operates at the site.

Eine europäische Wiederaufarbeitungsanlage

In den 1950er Jahren wollten mehrere westeuropäische Staaten eigene Erfahrungen mit der Wiederaufarbeitung bestrahlter Kernbrennstoffe sammeln. Zwölf Staaten unterzeichneten im Dezember 1957 den Gründungsvertrag für Eurochemic; mit dem späteren Beitritt Spaniens waren es 13. Die Bundesrepublik Deutschland und das französische CEA zeichneten mit jeweils 17 Prozent die größten ursprünglichen Kapitalanteile. Die gemeinsame Gesellschaft sollte Forschung, industrielle Erprobung und Ausbildung verbinden. Dessel, nahe dem belgischen Kernforschungszentrum Mol, bot dafür ein bereits nukleartechnisch geprägtes Umfeld.

Die Fabrik entstand von 1960 bis 1966. Für die damals unterschiedlichen Forschungs- und Leistungsreaktoren gab es keine einheitlichen Brennelemente. Eurochemic verarbeitete deshalb Brennstoffe verschiedener chemischer Zusammensetzung und Anreicherung. Die Anlage diente zugleich der Schulung zahlreicher Fachleute aus den beteiligten Ländern.

Konkurrenz der nationalen Anlagen

1966 begann der Betrieb; bis Ende 1974 wurden etwa 210 Tonnen bestrahlten Brennstoffs aufgearbeitet, darunter rund 30 Tonnen hochangereicherter Forschungsreaktorbrennstoffe.

Großbritannien und Frankreich verfügten mit Windscale und La Hague über wesentlich größere Anlagen beziehungsweise Ausbauprogramme. Auch die Bundesrepublik entwickelte mit der WAK in Karlsruhe, die 1971 den Betrieb aufnahm, eigene Wiederaufarbeitungstechnik. Am 12. Oktober 1971 vereinbarten die britische BNFL, das französische CEA und die deutsche KEWA die Gründung der United Reprocessors GmbH. Sie wollten Wiederaufarbeitungsleistungen gemeinsam vermarkten und die Auslastung bestehender sowie den Bau künftiger Anlagen aufeinander abstimmen. Die EG-Kommission ließ die Vereinbarung 1975 unter wettbewerbsrechtlichen Auflagen zu. Eurochemic blieb außerhalb dieser Organisation.

Für die vergleichsweise kleine Gemeinschaftsanlage fehlten die Aufträge. Im November 1971, wenige Wochen nach dieser Gründungsvereinbarung, beschloss der Eurochemic Verwaltungsrat, die Wiederaufarbeitung Ende 1974 einzustellen. Eine Wiederaufnahme wurde noch jahrelang erwogen; Mitte der 1980er Jahre fiel die endgültige Entscheidung dagegen.

Die Abfälle bleiben

Nach dem Betriebsende waren Prozesszellen, Behälter und Leitungen kontaminiert. Vor allem mussten die hochradioaktiven Flüssigabfälle der Wiederaufarbeitung verfestigt werden. Dafür entstand PAMELA – Pilotanlage Mol zur Erzeugung lagerfähiger Abfälle. An der Entwicklung waren die deutsche DWK und das Kernforschungszentrum Karlsruhe beteiligt. Von 1985 bis 1991 wurden dort rund 900 Kubikmeter hochradioaktiver Flüssigabfälle zu etwa 500 Tonnen Glasprodukt verarbeitet.

Die in Mol erprobte Verglasungstechnik wurde für die geplante deutsche Großanlage in Wackersdorf weiterentwickelt. Nach deren Aufgabe führten weitere Arbeiten zur Verglasungseinrichtung Karlsruhe (VEK). Sie verfestigte 2009 und 2010 die rund 60 Kubikmeter hochradioaktiver Flüssigabfälle aus dem Betrieb der WAK in 140 Glaskokillen.

1984 wurde Belgoprocess gegründet und übernahm die frühere Eurochemic-Anlage als Standort 1. 1989 kam die Abfallabteilung des belgischen Kernforschungszentrums SCK/CEN in Mol als Standort 2 hinzu. Diese Abteilung war in den 1987 aufgedeckten Transnuklear-Skandal verwickelt: Die Hanauer Transportfirma brachte radioaktive Abfälle aus deutschen Kernkraftwerken zur Behandlung nach Mol; bei der Rücklieferung wurden teilweise Abfälle anderer Herkunft falsch deklariert.

Unter Verantwortung von Belgoprocess begann 1990 der industrielle Rückbau der Eurochemic-Anlage. 2014 war der Abriss des Hauptgebäudes abgeschlossen – vierzig Jahre nach dem Ende der Wiederaufarbeitung.

A European reprocessing plant

During the 1950s, several Western European countries wanted to gain practical experience in reprocessing irradiated nuclear fuel. Twelve countries signed Eurochemic's founding agreement in December 1957; with Spain joining later, there were 13. The Federal Republic of Germany and the French CEA each subscribed 17 per cent, the largest initial shares of the capital. The joint enterprise was intended to combine research, industrial trials and training. Dessel, near Belgium's nuclear research centre at Mol, offered an environment in which nuclear technology was already well established.

The plant was built between 1960 and 1966. The research and power reactors of the period used many different fuel assemblies. Eurochemic therefore processed fuels with different chemical compositions and levels of enrichment. The plant also trained numerous specialists from the participating countries.

Competition from national plants

Operations began in 1966. By the end of 1974, approximately 210 tonnes of irradiated fuel had been reprocessed, including around 30 tonnes of highly enriched research reactor fuel.

Britain and France already had much larger plants or expansion programmes at Windscale and La Hague. West Germany was also developing its own reprocessing technology at the WAK in Karlsruhe, which began operating in 1971. On 12 October 1971, Britain's BNFL, France's CEA and Germany's KEWA agreed to establish United Reprocessors GmbH. Their aim was to market reprocessing services jointly and coordinate the utilisation of existing plants and construction of future facilities. In 1975, the European Commission approved the arrangement subject to competition-law conditions. Eurochemic remained outside this organisation.

The comparatively small joint plant lacked sufficient orders. In November 1971, just weeks after the agreement establishing United Reprocessors, Eurochemic's board decided to end reprocessing at the close of 1974. Restarting the plant remained under consideration for years; a final decision against it was taken in the mid-1980s.

The waste remains

When operations ceased, the process cells, vessels and pipework were contaminated. Above all, the high-level liquid waste from reprocessing had to be solidified. For this purpose, PAMELA was built — the Pilotanlage Mol zur Erzeugung lagerfähiger Abfälle (Mol pilot plant for producing waste suitable for storage). Germany's DWK and the Karlsruhe Nuclear Research Centre participated in its development. Between 1985 and 1991, around 900 cubic metres of high-level liquid waste were turned into approximately 500 tonnes of vitrified product.

The vitrification technology tested at Mol was developed further for the proposed large German plant at Wackersdorf. Following that project's cancellation, subsequent work led to the Karlsruhe Vitrification Facility (VEK). In 2009 and 2010, it solidified approximately 60 cubic metres of high-level liquid waste from WAK operations into 140 glass canisters.

Belgoprocess was founded in 1984 and took over the former Eurochemic plant as Site 1. In 1989, the waste department of Belgium's SCK/CEN nuclear research centre at Mol was added as Site 2. That department had been implicated in the Transnuklear scandal uncovered in 1987: the Hanau-based transport company brought radioactive waste from German nuclear power stations to Mol for treatment, and on its return some waste of other origins was incorrectly declared.

Industrial dismantling of the Eurochemic plant began under Belgoprocess in 1990. Demolition of the main building was completed in 2014 — forty years after reprocessing had ceased.

Technische EckdatenKey facts
Funktion
Wiederaufarbeitungsanlage (europäisches Gemeinschaftsunternehmen)
Bau und Betrieb
Bau 1960, Betrieb 1966–1974
Verarbeitete Menge gesamt
etwa 210 t bestrahlter Brennstoff (davon rund 30 t hochangereicherte Forschungsreaktorbrennstoffe)1966–1974
Rückbau
industrieller Rückbau ab 1990 (Belgoprocess); Abriss des Hauptgebäudes 2014 abgeschlossen
Technische EckdatenKey facts
Function
Reprocessing plant (European joint enterprise)
Construction and operation
construction from 1960, operation 1966–1974
Total quantity processed
approximately 210 tonnes of irradiated fuel (including around 30 tonnes of highly enriched research reactor fuel)1966–1974
Dismantling
industrial dismantling from 1990 (Belgoprocess); demolition of the main building completed in 2014