GRAZ: SIEMENS-ARGONAUT-REAKTOR
GRAZ: SIEMENS ARGONAUT REACTOR
An der Technischen Hochschule Graz betrieb man ab 1965 einen Siemens-Argonaut-Reaktor mit bis zu zehn Kilowatt thermischer Leistung. Er war eine deutsche Ausführung des amerikanischen Argonaut-Konzepts und diente der kerntechnischen Ausbildung und Reaktorphysik. Nach dem letzten Betrieb 2004 wurde die Anlage 2005/06 vollständig zurückgebaut.
From 1965, a Siemens Argonaut reactor with a thermal power of up to ten kilowatts was operated at Graz University of Technology. A German version of the American Argonaut design, it was used for nuclear engineering education and reactor physics. After its final operation in 2004, the facility was completely dismantled in 2005–06.
Ein amerikanischer Reaktortyp in deutscher Ausführung
Das Argonaut-Konzept entstand Mitte der 1950er Jahre am Argonne National Laboratory in den USA. Der kleine Ausbildungsreaktor sollte Hochschulen praktische Versuche mit einer geregelten Kernspaltung ermöglichen. Siemens entwickelte daraus eine eigene Ausführung und errichtete 1959 einen solchen Reaktor an der Technischen Hochschule München in Garching. Die Technische Hochschule Graz erhielt ebenfalls einen Siemens-Argonaut, dessen Leistung bis zu zehn Kilowatt erreichen konnte und damit deutlich höher lag als die des Garchinger SAR.
Am 17. Mai 1965 wurde der Grazer Reaktor erstmals kritisch. Im Dauerbetrieb war ein Kilowatt vorgesehen; zehn Kilowatt waren bei einer Betriebszeit von höchstens zwei Stunden täglich zulässig. Er diente der Ausbildung von Ingenieuren und Physikern sowie reaktorphysikalischen Messungen. Gleichzeitig betrieb das Wiener Atominstitut den amerikanischen Forschungsreaktor TRIGA, während Seibersdorf mit ASTRA über eine leistungsfähige Neutronenquelle für Forschung und Isotopenproduktion verfügte.
Rückbau
Der letzte Betrieb des Grazer SAR fand am 31. Juli 2004 statt. Von 5. Dezember 2005 bis 25. Oktober 2006 wurde er dekommissioniert. Nach Entfernung der Brennelemente und dem Abbau der aktivierten und kontaminierten Teile konnte die frühere Reaktorhalle freigegeben werden.
An American reactor design in a German version
The Argonaut concept originated at Argonne National Laboratory in the United States in the mid-1950s. The small training reactor was intended to give university students practical experience with controlled nuclear fission. Siemens developed its own version and built such a reactor in 1959 at the Technical University of Munich in Garching. Graz University of Technology also received a Siemens Argonaut reactor, capable of up to ten kilowatts and therefore substantially more powerful than the Garching SAR.
The Graz reactor first achieved criticality on 17 May 1965. One kilowatt was specified for continuous operation; ten kilowatts were permitted for up to two hours per day. It was used to train engineers and physicists and for reactor physics measurements. At the same time, Vienna's Atominstitut operated an American TRIGA research reactor, while Seibersdorf's ASTRA was a powerful neutron source for research and isotope production.
Dismantling
The Graz SAR last operated on 31 July 2004. It was decommissioned between 5 December 2005 and 25 October 2006. Once the fuel elements had been removed and the activated and contaminated components dismantled, the former reactor hall could be released from regulatory control.
- Reaktortyp
- Argonaut-Reaktor
- Hersteller
- Siemens
- Betreiber
- Verein zur Förderung der Strahlenforschung (Reaktorinstitut Graz)
- Leistung thermisch
- 1 kW Dauerbetrieb; bis 10 kW bei zeitlich begrenztem Betrieb
- Erstkritikalität
- 17.5.1965
- Rückbau
- Rückbau 5.12.2005–25.10.2006
- Status
- rückgebaut
- letzter Betrieb 31.7.2004
Betreiber
Ursprünglich Verein zur Förderung der Anwendung der Kernenergie; wissenschaftlicher Betrieb am Reaktorinstitut Graz, TU Graz.
- Reactor type
- Argonaut reactor
- Manufacturer
- Siemens
- Operator
- Association for the Promotion of Radiation Research (Reactor Institute Graz)
- Thermal power
- 1 kW continuous operation; up to 10 kW for limited periods
- First criticality
- 17 May 1965
- Decommissioning
- Dismantling 5 December 2005 – 25 October 2006
- Status
- Dismantled
- Last operation: 31 July 2004
Operator
Originally the Association for the Promotion of the Use of Nuclear Energy; scientific operation at the Reactor Institute Graz, Graz University of Technology.