Karlstein:

HDR GROSSWELZHEIM

Der von AEG gebaute Heißdampfreaktor Großwelzheim sollte Dampf direkt im Reaktor überhitzen. Der 1969 erstmals kritische Prototyp wurde 1971 nach Brennelementschäden aufgegeben. Sein Gebäude diente anschließend bis 1991 für Versuche zur Reaktorsicherheit, unter anderem zu Erdbeben und äußeren Einwirkungen. 1998 war der Abbau abgeschlossen.

The Großwelzheim superheated steam reactor, built by AEG, was designed to superheat steam directly inside the reactor. The prototype first achieved criticality in 1969 but was abandoned in 1971 following fuel element damage. Its building was subsequently used for reactor safety experiments until 1991, including tests involving earthquakes and external impacts. Dismantling was completed in 1998.

Der Heißdampfreaktor Großwelzheim wurde ab 1965 nach Entwürfen der AEG errichtet. Ziel war ein Reaktor, der den erzeugten Wasserdampf im Reaktorkern weiter erhitzte und so die üblichen Heißdampfturbinen mit höherem Wirkungsgrad betreiben konnte. Die Entwicklung der empfindlichen Brennelemente wurde zuvor auch im benachbarten VAK erprobt. Das staatlich geförderte Versuchsvorhaben wurde von der Heißdampfreaktor-Betriebsgesellschaft mbH betrieben. Letzter atomrechtlicher Genehmigungsinhaber war das Forschungszentrum Karlsruhe.

Der HDR besaß keinen eigenen Turbosatz. Sein Dampf wurde über eine Leitung einer bereits vorhandenen Heißdampfturbine zugeführt. Am 14. Oktober 1969 erreichte der Reaktor erstmals die Kritikalität; am 2. August 1970 wurde seine Dampfabgabe an die Turbine aufgenommen. Vorgesehen waren 100 Megawatt thermisch und 25 Megawatt elektrisch. Schon während der Inbetriebsetzung hatten Brennelemente und Dampfführungen Schwierigkeiten bereitet. Im Frühjahr 1971 traten nach Leistungsversuchen Schäden und Undichtigkeiten an Brennelementhüllen auf. Am 20. April 1971 wurde der Reaktor abgeschaltet und danach nicht wieder in Betrieb genommen.

1974 wurde der Kern entladen. Das vorhandene Reaktorgebäude und die eingebauten Systeme wurden anschließend für große nichtnukleare Sicherheitsversuche genutzt. Die Forscher prüften unter anderem das Schwingungsverhalten von Gebäude, Behältern und Rohrleitungen bei künstlichen Erdbeben, simulierten Rohrbrüche, Brandereignisse und äußere Einwirkungen. Die Versuchsprogramme liefen bis 1991. Von 1995 bis 1998 wurde die Anlage vollständig abgebaut.

Construction of the Großwelzheim superheated steam reactor began in 1965 to designs by AEG. The aim was to develop a reactor that heated the steam it produced still further inside the core, allowing conventional superheated-steam turbines to operate at higher efficiency. Development of the sensitive fuel elements had previously been tested at the neighbouring VAK reactor. The publicly funded experimental project was operated by Heißdampfreaktor-Betriebsgesellschaft mbH. The last holder of its nuclear licence was Forschungszentrum Karlsruhe.

The HDR had no turbine-generator set of its own. Steam was supplied through a pipe to an existing superheated-steam turbine. The reactor first achieved criticality on 14 October 1969; steam delivery to the turbine began on 2 August 1970. The design ratings were 100 megawatts thermal and 25 megawatts electrical. Problems with fuel elements and steam ducts had already arisen during commissioning. In spring 1971, power tests were followed by damage and leaks in fuel cladding. The reactor was shut down on 20 April 1971 and was never restarted.

The core was unloaded in 1974. The existing reactor building and installed systems were then used for large-scale non-nuclear safety tests. Researchers examined, among other things, how the building, vessels and pipework responded to simulated earthquakes; they also simulated pipe ruptures, fires and external impacts. The experimental programmes continued until 1991. The facility was completely dismantled between 1995 and 1998.

Technische EckdatenKey facts
Reaktortyp
Siedewasserreaktor
Bauart / Modell
Heißdampfreaktor
Hersteller
AEG
Betreiber
Forschungszentrum Karlsruhe
Leistung thermisch
100 MW
Leistung elektrisch
25 MW
Erstkritikalität
14.10.1969
Netzanschluss
2.8.1970
Abschaltung
20.4.1971
Rückbau
vollständiger Abbau 1998
Status
rückgebaut
Dampfabgabe an eine angeschlossene Turbine
nichtnukleare Sicherheitsversuche 1974–1991
Direkte nukleare Dampfüberhitzung
Technische EckdatenKey facts
Reactor type
Boiling water reactor
Design / model
Superheated steam reactor
Manufacturer
AEG
Operator
Forschungszentrum Karlsruhe
Thermal power
100 MW
Electrical power
25 MW
First criticality
14.10.1969
Grid connection
2.8.1970
Shutdown
20.4.1971
Dismantling
completed in 1998
Status
dismantled
Steam supplied to a connected turbine
Non-nuclear safety experiments 1974–1991
Direct nuclear steam superheating