SCHACHT KONRAD

KONRAD MINE

In Salzgitter wird ein ehemaliges Eisenerzbergwerk zum Endlager für radioaktive Abfälle mit vernachlässigbarer Wärmeentwicklung umgebaut. Die Erzförderung endete 1976, der Endlagerplan wurde 2002 genehmigt und 2007 rechtskräftig. Unter Tage entstehen Einlagerungsbereiche in rund 850 Metern Tiefe. Die vorgesehenen 303.000 Kubikmeter Abfall sind noch nicht eingelagert; der Betriebsbeginn wird inzwischen für die frühen 2030er Jahre erwartet.

In Salzgitter, a former iron-ore mine is being converted into a repository for radioactive waste that generates negligible heat. Ore production ended in 1976; the repository plan was approved in 2002 and became legally binding in 2007. Underground disposal areas are being created at a depth of about 850 metres. None of the planned 303,000 cubic metres of waste has yet been emplaced; operations are now expected to begin in the early 2030s.

Eisenerz unter Salzgitter

1933 wurde bei der Suche nach Erdöl tief unter Salzgitter eine Eisenerzlagerstätte entdeckt. In den 1950er Jahren begann die Erschließung durch zwei Schächte. Schacht Konrad 1 erreichte 1960 eine Tiefe von 1.232 Metern; Konrad 2 entstand etwa 1,8 Kilometer südöstlich auf dem Gelände der damaligen Salzgitter Hütte. Von 1964 bis 1976 wurde Erz gefördert. Dann endete der Betrieb, weil sich die Gewinnung wirtschaftlich nicht mehr lohnte.

Während der Stilllegung des Bergwerks begann seine Untersuchung als möglicher Standort für radioaktive Abfälle. Das Bergwerk gilt für eine Eisenerzgrube als außergewöhnlich trocken. Über dem Erzhorizont liegen 160 bis 400 Meter mächtige Tonsteinschichten, die den Wasserzutritt begrenzen. Diese Verhältnisse gaben den Ausschlag für die geologischen Eignungsuntersuchungen ab 1975.

Drei Jahrzehnte Genehmigungsverfahren

1982 leitete die Physikalisch-Technische Bundesanstalt das atomrechtliche Planfeststellungsverfahren ein. Die Unterlagen wurden umfangreich überarbeitet, ehe die Öffentlichkeit beteiligt werden konnte. Bei der Auslegung gingen rund 290.000 Einwendungen ein. Der Erörterungstermin in Salzgitter dauerte von September 1992 bis März 1993, insgesamt 75 Verhandlungstage.

Im Mai 2002 genehmigte Niedersachsen das Endlager. Nach mehreren Klagen bestätigten die Gerichte die Entscheidung; 2007 wurde der Planfeststellungsbeschluss rechtskräftig. Der Genehmigungsrahmen erlaubt die Einlagerung von bis zu 303.000 Kubikmetern radioaktiven Abfalls mit vernachlässigbarer Wärmeentwicklung. Dazu zählen Betriebs- und Rückbauabfälle aus Kernkraftwerken und Forschungseinrichtungen, jedoch keine abgebrannten Brennelemente oder hochradioaktiven Glaskokillen.

Die genehmigte Kapazität reicht nicht für sämtliche deutschen Abfälle dieser Kategorie. Die Bundesregierung rechnet bei einer Rückholung der Abfälle aus der Asse II mit einem zusätzlichen Endlagervolumen von bis zu 220.000 Kubikmetern. Hinzu kommen möglicherweise bis zu 100.000 Kubikmeter aus der Urananreicherung, unter anderem aus Gronau, falls diese Stoffe nicht weiterverwertet werden. Für solche Mengen ist ein weiteres Endlager vorgesehen; geprüft werden soll auch eine Anbindung an den noch zu findenden Standort für hochradioaktive Abfälle.

Widerstand gegen das Vorhaben blieb bestehen. Ein Antrag von BUND und NABU auf Rücknahme oder Widerruf des Planfeststellungsbeschlusses wurde von Niedersachsen 2024 abgelehnt.

Umbau eines alten Bergwerks

Für das Endlager werden neue Einlagerungsräume in rund 850 Metern Tiefe geschaffen und die beiden Schächte technisch erneuert. Über Konrad 2 sollen die angelieferten Gebinde später nach unter Tage transportiert werden; Konrad 1 dient im vorgesehenen Betrieb vor allem der Versorgung und Bewetterung. In den Einlagerungskammern sollen die Gebinde nach festgelegten Verfahren eingebracht und Hohlräume mit geeignetem Material verfüllt werden.

Der Umbau dauert erheblich länger als ursprünglich erwartet. Vor allem die Herrichtung des Einlagerungsschachts Konrad 2 erwies sich als zeitbestimmend. Im Oktober 2026 waren die unterirdischen Einlagerungsbereiche hergestellt und wesentliche Gebäude auf Konrad 1 fertiggestellt; an Konrad 2 wurde weiter an Förderturm, Umladehalle und technischer Infrastruktur gebaut. Die ehemals angestrebte Fertigstellung 2027 ist nicht mehr erreichbar. Die BGE nennt nun die frühen 2030er Jahre für den Beginn der Einlagerung.

Die BGE schätzt die Errichtungskosten auf rund 5,8 Milliarden Euro, zusätzlich zu etwa 930 Millionen Euro für Erkundung und Planung zwischen 1977 und 2007.

Iron ore beneath Salzgitter

In 1933, a deposit of iron ore was discovered deep beneath Salzgitter during a search for oil. Development using two shafts began in the 1950s. Konrad Shaft 1 reached a depth of 1,232 metres in 1960; Konrad 2 was constructed about 1.8 kilometres to the south-east, on the site of the then Salzgitter steelworks. Ore was mined from 1964 to 1976. Operations then ceased because extraction was no longer economically viable.

As the mine was being closed, investigations began into its possible use for radioactive waste. The mine is considered exceptionally dry for an iron-ore mine. Above the ore-bearing horizon are mudstone layers 160 to 400 metres thick, which restrict the ingress of water. These conditions were decisive in the geological suitability investigations that began in 1975.

Three decades of licensing proceedings

In 1982, the Physikalisch-Technische Bundesanstalt (Federal Institute of Physics and Metrology) initiated the nuclear-law plan approval procedure. The documentation underwent extensive revisions before the public could be consulted. Around 290,000 objections were submitted during the public display. The hearing in Salzgitter lasted from September 1992 to March 1993, comprising 75 days of proceedings.

In May 2002, Lower Saxony approved the repository. Following several legal challenges, the courts upheld the decision; the plan approval became legally binding in 2007. The permit allows the emplacement of up to 303,000 cubic metres of radioactive waste that generates negligible heat. This includes operational and decommissioning waste from nuclear power plants and research facilities, but not spent nuclear fuel or vitrified high-level waste canisters.

The approved capacity is insufficient for all German waste in this category. If waste is retrieved from Asse II, the Federal Government expects an additional repository volume of up to 220,000 cubic metres to be required. There may also be up to 100,000 cubic metres from uranium enrichment, including Gronau, if these materials are not reused. A further repository is envisaged for such quantities; a connection to the as-yet unidentified site for high-level radioactive waste is also to be examined.

Opposition to the project continued. In 2024, Lower Saxony rejected a request by the environmental organisations BUND and NABU to withdraw or revoke the plan approval decision.

Converting an old mine

New disposal chambers are being constructed at a depth of about 850 metres, and the two shafts are being technically upgraded. Waste packages are intended to be transported underground through Konrad 2; during future operation, Konrad 1 will mainly serve supplies and ventilation. Waste packages will be emplaced in the disposal chambers according to prescribed procedures, and the remaining voids filled with suitable material.

Conversion is taking considerably longer than originally anticipated. Preparing Konrad 2, the waste-emplacement shaft, has proved particularly critical to the schedule. By October 2026, the underground disposal areas had been completed and major buildings at Konrad 1 were finished; work at Konrad 2 continued on the headframe, transfer hall and technical infrastructure. The previously targeted completion date of 2027 is no longer achievable. BGE now expects emplacement to begin in the early 2030s.

BGE estimates construction costs at approximately €5.8 billion, in addition to around €930 million spent on exploration and planning between 1977 and 2007.

Technische EckdatenKey facts
Typ
Endlager im Umbau (ehemaliges Eisenerzbergwerk, Salzgitter)
Planfeststellungsbeschluss
Mai 2002, rechtskräftig 2007
Genehmigte Kapazität
303.000 m³ verpackte Abfälle mit vernachlässigbarer Wärmeentwicklung
Einlagerungstiefe
rund 850 m
Geplanter Einlagerungsbeginn
Anfang der 2030er-Jahre (Planung der BGE, Stand 2026)
Vorhabenträgerin / künftige Betreiberin
BGE
Technische EckdatenKey facts
Type
Repository under construction (former iron-ore mine, Salzgitter)
Plan approval
May 2002, legally binding since 2007
Approved capacity
303,000 m³ of packaged waste generating negligible heat
Disposal depth
approximately 850 m
Planned start of waste emplacement
early 2030s (BGE planning estimate, as of 2026)
Project developer / future operator
BGE