KERNKRAFTWERK MÜLHEIM-KÄRLICH
MÜLHEIM-KÄRLICH NUCLEAR POWER PLANT
Das Kernkraftwerk Mülheim-Kärlich am Rhein bei Koblenz war ein Sonderweg im westdeutschen Reaktorbau. Statt eines Druckwasserreaktors der Kraftwerk Union ließ RWE einen Reaktor nach amerikanischer Babcock-&-Wilcox-Technik errichten. Der Bau dauerte elf Jahre; nach nur rund 13 Monaten kommerziellem Leistungsbetrieb wurde die Anlage 1988 infolge eines Gerichtsurteils abgeschaltet und nie wieder angefahren. Der weithin sichtbare Kühlturm wurde 2019 abgebrochen.
Mülheim-Kärlich Nuclear Power Plant on the Rhine near Koblenz followed an unusual path in West German reactor construction. Instead of a Kraftwerk Union pressurised water reactor, RWE commissioned a plant based on American Babcock & Wilcox technology. Construction took eleven years. After only about 13 months of commercial operation, a court ruling forced the plant to shut down in 1988; it never restarted. Its prominent cooling tower was demolished in 2019.
Ein anderer Lieferant
Anfang der 1970er-Jahre plante RWE ein großes Kernkraftwerk am linken Rheinufer nördlich von Koblenz. Der Standort lag im Neuwieder Becken, einer geologisch und seismisch besonders sorgfältig zu untersuchenden Region. Im Januar 1973 erhielt ein Konsortium unter Führung von Brown, Boveri & Cie (BBC) den Auftrag zum Bau. Die Brown Boveri Reaktor GmbH (BBR) lieferte das nukleare Dampferzeugungssystem auf Basis einer Lizenz des amerikanischen Herstellers Babcock & Wilcox; den Bau übernahm Hochtief.
Während die großen deutschen Druckwasserreaktoren zunehmend von der Kraftwerk Union geliefert wurden, entstand hier eine abweichende Konstruktion mit einem eigenen Genehmigungs- und Technikweg. Der Bau begann im Januar 1975. Die Anlagentechnik musste an die deutschen Sicherheitsanforderungen angepasst werden; nach dem Reaktorunfall von Three Mile Island bei Harrisburg 1979 kamen weitere Überprüfungen hinzu. Der dort havarierte Reaktor war ebenfalls von Babcock & Wilcox geliefert worden; die Untersuchungen betrafen deshalb unmittelbar auch die sicherheitstechnische Konzeption von Mülheim-Kärlich.
70 Meter neben der Genehmigung
Während der Planung hatte sich herausgestellt, dass der ursprünglich vorgesehene Standort des Reaktorgebäudes über einer geologischen Störungszone lag. Das Reaktorgebäude und das Maschinenhaus wurden deshalb um rund 70 Meter verschoben. Die Änderung wurde in der zweiten Teilgenehmigung berücksichtigt, nicht aber in der bereits erteilten ersten Teilgenehmigung von Januar 1975 nachgetragen. Die erneute öffentliche Erörterung der veränderten Planung unterblieb. Im Neuwieder Becken, dessen Untergrund von geologischen Störungen geprägt ist, war die Lage des Reaktorgebäudes keine bloße Formalität.
Der lange Weg ans Netz
Am 1. März 1986 erreichte der Reaktor erstmals die Kritikalität, am 14. März speiste er zum ersten Mal Strom ins Netz. Das Oberverwaltungsgericht Koblenz stoppte den Betrieb im Oktober 1986 wegen fehlender immissionsschutzrechtlicher Genehmigungen für den Kühlturm. Erst im August 1987 konnte der kommerzielle Leistungsbetrieb beginnen.
Der Naturzugkühlturm war mit 162 Metern Höhe und etwa 120 Metern Durchmesser am Fuß eine weithin sichtbare Landmarke des Mittelrheingebiets. Sein Erscheinungsbild prägte das Kraftwerk weit stärker als die vergleichsweise niedrige Kuppel des Reaktorgebäudes.
Das Urteil vom 9. September 1988
Am 9. September 1988 hob das Bundesverwaltungsgericht die erste Teilerrichtungsgenehmigung auf: Sie bezog sich noch auf die ursprüngliche Standortplanung, während das Kraftwerk an der verschobenen Position errichtet worden war. Zudem waren die geologischen Standortverhältnisse nicht ausreichend ermittelt und bewertet worden. Der Reaktor wurde noch am selben Tag abgeschaltet. Obwohl in den Folgejahren neue Genehmigungsversuche unternommen wurden, kehrte die Anlage nie in den Leistungsbetrieb zurück. Über ihre gesamte Lebensdauer erzeugte sie rund elf Milliarden Kilowattstunden Strom.
Die Anlage blieb über Jahre betriebsbereit, während sich die Genehmigungsstreitigkeiten fortsetzten. Auch eine neu erteilte erste Teilgenehmigung wurde später gerichtlich aufgehoben.
107 Terawattstunden ohne Reaktor
Im Atomkonsens von 2000/2001 verzichtete RWE endgültig auf die Wiederinbetriebnahme, nahm den Genehmigungsantrag und die Schadensersatzklage gegen Rheinland-Pfalz zurück. Dafür erhielt der Konzern das Recht, 107,25 Terawattstunden als Reststrommenge auf bestimmte andere Kernkraftwerke zu übertragen, darunter Emsland, Isar 2, Neckarwestheim II und Brokdorf sowie Gundremmingen B und C und in begrenztem Umfang Biblis B. Diese Strommenge entsprach rund dem Zehnfachen der etwa 11 Terawattstunden, die Mülheim-Kärlich während seiner kurzen Betriebszeit selbst erzeugt hatte.
Ein Kühlturm verschwindet
2004 begann der genehmigte Rückbau. Maschinenhaus und mehrere Nebengebäude wurden später abgetragen, die Brennelemente hatten das Kraftwerk bereits 2002 verlassen.
Für den Abbruch des Kühlturms wurde zunächst ein Spezialbagger auf die obere Turmkante gehoben, der die Betonschale abschnittsweise abtrug. Als nur noch etwa die halbe Höhe übrig war, wurde die verbliebene Konstruktion gezielt geschwächt. Am 9. August 2019 brachten ferngesteuerte Bagger tragende Stützen zum Versagen; der Turm stürzte kontrolliert in sich zusammen. Der Rückbau der übrigen Anlage wird fortgesetzt.
A different supplier
In the early 1970s, RWE planned a large nuclear power station on the Rhine’s left bank north of Koblenz. The site lay in the Neuwied Basin, an area requiring particularly careful geological and seismic investigation. In January 1973, a consortium led by Brown, Boveri & Cie (BBC) received the construction contract. Brown Boveri Reaktor GmbH (BBR) supplied the nuclear steam supply system under licence from the American manufacturer Babcock & Wilcox; Hochtief undertook the building works.
While Kraftwerk Union was increasingly supplying Germany’s large pressurised water reactors, Mülheim-Kärlich followed a different design and a separate technical and licensing path. Construction began in January 1975. The plant technology had to be adapted to German safety requirements. Further reviews followed the 1979 accident at Three Mile Island near Harrisburg. That reactor, too, had been supplied by Babcock & Wilcox, so the investigations had direct implications for the safety design of Mülheim-Kärlich.
Seventy metres away from the licensed position
During planning, it emerged that the originally proposed reactor building site lay above a geological fault zone. The reactor and turbine buildings were therefore moved by approximately 70 metres. The change was incorporated into the second partial construction licence but not added to the first, which had already been issued in January 1975. No further public hearing was held on the revised plans. In the Neuwied Basin, with its geologically faulted subsurface, the position of the reactor building was not merely a formality.
The long road to the grid
The reactor first achieved criticality on 1 March 1986 and supplied electricity to the grid for the first time on 14 March. In October 1986, the Higher Administrative Court in Koblenz halted operation because the cooling tower lacked the necessary permits under air-pollution control law. Commercial operation did not begin until August 1987.
Standing 162 metres high and measuring around 120 metres across at its base, the natural-draught cooling tower was a landmark visible across the Middle Rhine region. It dominated the appearance of the plant far more than the comparatively low dome of the reactor building.
The judgment of 9 September 1988
On 9 September 1988, the Federal Administrative Court annulled the first partial construction licence: it still referred to the original site plan, whereas the power station had been built in the relocated position. In addition, the geological conditions at the site had not been adequately investigated and assessed. The reactor was shut down that same day. Although new licensing attempts followed, it never returned to power operation. Over its entire lifetime it generated approximately eleven billion kilowatt-hours of electricity.
The plant remained capable of operating for years while the licensing disputes continued. A newly issued first partial construction licence was also later overturned in court.
107 terawatt-hours without a reactor
Under the nuclear phase-out agreement of 2000–2001, RWE finally abandoned plans to restart the plant and withdrew both its licensing application and its claim for damages against the state of Rhineland-Palatinate. In return, the group was allowed to transfer 107.25 terawatt-hours of residual electricity generation entitlement to specified other nuclear power stations. These included Emsland, Isar 2, Neckarwestheim II and Brokdorf, as well as Gundremmingen B and C and, to a limited extent, Biblis B. The entitlement was roughly ten times the 11 terawatt-hours Mülheim-Kärlich itself had generated during its short operating life.
A cooling tower disappears
Licensed dismantling began in 2004. The turbine hall and several ancillary buildings were subsequently demolished; the fuel assemblies had already left the plant in 2002.
To demolish the cooling tower, a specialist excavator was first lifted onto its upper rim and used to remove the concrete shell section by section. Once only about half its original height remained, the structure was deliberately weakened. On 9 August 2019, remotely operated excavators caused load-bearing supports to fail, and the tower collapsed in a controlled manner. Dismantling of the rest of the plant continues.
- Reaktortyp
- Druckwasserreaktor
- Hersteller
- Brown Boveri Reaktor GmbH (BBR)
- Betreiber
- RWE Energie AG
- Leistung thermisch
- 3.760 MW
- Leistung elektrisch
- 1.302 / 1.219 MW
- Primärkreisläufe
- 4 / 2
- Baubeginn
- 16.1.1975
- Erstkritikalität
- 1.3.1986
- Netzanschluss
- 14.3.1986
- Kommerzieller Betrieb
- 18.8.1987 (Bund-Länder-Portal)
- Abschaltung
- 9.9.1988
- Status
- im Rückbau
- Kühlung: Naturzugkühlturm (162 m; 2019 abgebrochen)
- Erste Stilllegungs- und Abbaugenehmigung: 16.7.2004
- Babcock-&-Wilcox-Lizenztechnik
- Primärsystem: vier Hauptkühlmittelpumpen und zwei Dampferzeuger (4 / 2); abweichende Babcock-&-Wilcox-Anordnung
- Reactor type
- Pressurised water reactor
- Manufacturer
- Brown Boveri Reaktor GmbH (BBR)
- Operator
- RWE Energie AG
- Thermal output
- 3,760 MW
- Electrical output
- 1,302 / 1,219 MW
- Primary coolant loops
- 4 / 2
- Construction began
- 16 January 1975
- First criticality
- 1 March 1986
- Grid connection
- 14 March 1986
- Commercial operation
- 18 August 1987 (federal–state nuclear safety portal)
- Shutdown
- 9 September 1988
- Status
- Under dismantling
- Cooling: Natural-draught cooling tower (162 m; demolished in 2019)
- First decommissioning and dismantling licence: 16 July 2004
- Babcock & Wilcox licensed technology
- Primary system: Four main coolant pumps and two steam generators (4 / 2); an arrangement differing from the standard German KWU design
Glossar:Glossary:
Druckwasserreaktor (DWR)
Leichtwasserreaktor, in dem Wasser unter einem Druck von etwa 150 bis 160 bar durch den Reaktorkern strömt, ohne dort zu sieden. Es kühlt die Brennelemente und bremst als Moderator die Neutronen. Über Dampferzeuger gibt der geschlossene Primärkreislauf seine Wärme an einen getrennten Sekundärkreislauf ab, dessen Dampf die Turbine antreibt. Die beiden Wasserkreisläufe vermischen sich nicht; im Normalbetrieb bleibt das radioaktive Reaktorkühlmittel vom Turbinenkreislauf getrennt. Ein Druckhalter stabilisiert den Druck im Primärkreislauf.
Das Konzept wurde in den USA zunächst für den Antrieb von U-Booten entwickelt. Unter Leitung von Hyman G. Rickover entstand bei Westinghouse der Reaktor für die USS Nautilus, die 1954 in Dienst gestellt wurde und 1955 erstmals mit Kernenergie fuhr. Im Kraftwerk Shippingport ging 1957 ein Druckwasserreaktor zur Stromerzeugung ans Netz. Siemens übernahm die amerikanische Technik; die Kraftwerk Union (KWU) entwickelte daraus die westdeutsche Linie bis zum Konvoi. Dessen Entwicklung floss zusammen mit der französischen N4-Baureihe in den Europäischen Druckwasserreaktor EPR ein. Die sowjetischen und russischen WWER bilden eine eigenständige Druckwasserreaktorlinie – auf der Karte vertreten durch Rheinsberg, Greifswald und das nicht fertiggestellte Kernkraftwerk Stendal.
Glossar:Glossary:
Pressurised Water Reactor (PWR)
A light-water reactor in which water flows through the reactor core at a pressure of approximately 150–160 bar without boiling. It cools the fuel assemblies and acts as a moderator, slowing the neutrons. The closed primary circuit transfers its heat through steam generators to a separate secondary circuit, whose steam drives the turbine. The water in the two circuits does not mix; under normal operating conditions, the radioactive reactor coolant remains separate from the turbine circuit. A pressuriser stabilises the pressure in the primary circuit.
The concept was originally developed in the United States for submarine propulsion. Under the direction of Hyman G. Rickover, Westinghouse developed the reactor for the USS Nautilus, which entered service in 1954 and made its first nuclear-powered voyage in 1955. A pressurised water reactor at Shippingport began supplying electricity to the grid in 1957. Siemens adopted the American technology; Kraftwerk Union (KWU) developed it into the West German reactor line culminating in the Konvoi. Together with the French N4 series, this design development contributed to the European Pressurised Reactor (EPR). The Soviet and Russian WWER reactors represent an independent pressurised water reactor line, represented on the map by Rheinsberg, Greifswald and the unfinished Stendal nuclear power station.